Consultant Company on the project was CNEC Engenharia. The dam is located on the Uruguai river in the state of Santa Catarina in southern Brazil. Annual precipitation in this area is approximately 1750 mm with heavy rain in December to March. It was essential for the client to choose a design whereby the construction process could be very fast with little interruption because of the frequent rainy conditions.
Project description
Asphalt works started in December 2009 and were completed in the middle of April 2010.
Previous standards have called for asphalt to be laid in 20 cm layers. The layer thickness was here increased to 25 cm layers after performing trials that documented that up to 4 layers of 25 cm each could be laid without any detrimental effect on the void content or permeability of the laid asphalt. Void content measurements based on core drilling were regularly performed and proved that the laid asphalt core has a void of less than 1.5%, or a permeability of less than 10-11 cm/sec.
The 47 m high asphalt core was built laying 1 to 3 layers per day, each 25cm thick following the infilling of the dam body.
Cammargo Corrêa supplied the asphalt plant, ordinary machinery, personnel and laboratory services while Kolo Veidekke supplied special machinery and supervisory staff.
Dimensions
Maximum dam height | 47 m |
Length of crest | 600 m |
Dam volume | 1.5 million m3 |
Asphalt volume | 17.000 m3 |
Asphalt core thickness | 0.55cm |
Upstream slope | 1:1.4 |
Downstream slope | 1:1.4 |